February 2019 Progress

We got the gym cleaned up to check the floor for flatness and got half the walls painted and worked on installing more casework and vanities. We also worked on the wood ceiling in the lobby and started flooring on 2nd floor. We finished flooring on the 2nd floor and...

January 2019 Progress

We got a good portion of the gym painted, installed the window on the East end of the gym, and started hanging light fixtures. We also installed the wood and the mantels on both fireplaces. We worked on installing light fixtures and installing interior windows. We...

December 2018 Progress

We finished the remodel of the office area and the YMCA moved in all of their furniture and continued painting in area B of the new addition. We got the field-house enclosed this week and turned the permanent heat on. We also finished the running track and it is ready...

November 2018 Progress

We finished the site concrete, continued painting the field-house, enclosed area B and started heating the building. We also continued hanging drywall and were taping the drywall in the existing building. The main stairs were installed by the lobby, and the fireplaces...

October 2018 Progress

This month we started demo of the main entrance of the existing building. We also started hanging drywall in the new addition for phase #2. The field-house framing is almost complete and the new main entrance stone veneer is also complete. We worked on rough ins and...