September 2018 Progress

We continued setting precast for the field house and finished the roof on area B. We continued to set the roof joints for the field house and finished the masonry veneer along the existing building on the roof. We started installing in-wall backing and interior window...

August 2018 Progress

This week we finished the masonry firewall on 2nd floor.  We also started setting structural steel for the roof. The hill that was the old parking lot is now gone and we were able to finish digging out the pond. We continued the underground plumbing inside the new...

July 2018 Progress

We have started setting structural steel in area B, We also finished excavating for the field house and worked on foundations for the field house. We also finished setting precast for 2nd floor area B, and started the masonry firewall on 2nd floor and also started...

May 2018 Progress

This month most of the flooring and ceiling tile were installed on 1st floor and kitchen equipment started to get installed. Most of the flooring and finishes were installed on 2nd floor. We also continued with the longboard on the South side and started to install...

March 2018 Progress

We continued to hang drywall on 1st floor and started to tape and finish the joints and also started to hang drywall on 2nd floor and install electrical equipment in the mechanical room. We started the cavity wall insulation on the North side, worked on framing the...