This month we got the entire building enclosed. We are almost done framing walls on 1st floor and have a lot of the mechanicals roughed in. We worked on installing the stairs at the main entrance of the addition and also started installing the roof this week. We were...
This month we were able to get most of the exterior studs up on 1st floor and start the exterior sheathing. We also worked on the roof framing and got the sheathing done on the North side and started to install the air and vapor barrier. We also got a lot of the...
The masons finished the stair shaft and took all of their scaffold down, we also worked on getting the new parking lot graded before everything freezes. We were able to get half of the slab on grade poured this week with the warmer weather. We also have a warm place...
We finished the elevator shaft the week of November 18th, we also started the stair shaft on the West side and got a lot of the underground plumbing installed. The site was staked out this week and we will start prepping for the new parking...
The past few weeks were crazy busy, but we were able to get occupancy this week and the YMCA can start using the space. We also moved all of their equipment from the fitness center down to the gym so we can start interior demo for phase #2.The parking lot was also...