We finished the remodel of the office area and the YMCA moved in all of their furniture and continued painting in area B of the new addition. We got the field-house enclosed this week and turned the permanent heat on. We also finished the running track and it is ready for concrete. We continued work on the 2nd phase of the existing building area B and we started to install light fixtures and bathroom fixtures. We also installed all of the gym equipment. We installed the door to the roof patio and started to install interior windows. The exterior signage is installed and we continued with the metal panels. We got the permanent lighting going in the fitness center and painted the walls on 1st floor.