We finished the site concrete, continued painting the field-house, enclosed area B and started heating the building. We also continued hanging drywall and were taping the drywall in the existing building. The main stairs were installed by the lobby, and the fireplaces were installed. We also continued installing the running track in the field-house. We are just about done with the remodel portion of the office area in the existing building. We also started painting in area B of the new addition and finished the stone veneer on the fireplace and the wall at the main entrance. We also continued installing the running track in the field-house and were able to finish the parking lot blacktop and striping before the weather turned too cold.